Sidmouth £21 million coastal defence scheme step forward

Sidmouth from above. <i>(Image: EDDC)</i>
Sidmouth from above. (Image: EDDC)
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.

A major coastal defence scheme has taken a significant step forward.

The £21 million project aims to protect Sidmouth’s seafront and town from flooding and erosion for the next 100 years under a plan backed by East Devon District Council (EDDC).

The scheme focuses on the stretch between Jacob’s Ladder and East Beach and includes a mix of breakwaters, beach recharging, and a ‘super groyne’ or offshore structure to retain the new shingle.

Cllr Geoff Jung, EDDC’s portfolio holder for environment operations, said: "We recognise how important this coastal defence scheme is for the people of Sidmouth.

"The team is confident that good planning and teamwork will ensure the project succeeds in protecting Sidmouth’s coast.

"We’re fully committed to moving ahead positively, and we’re grateful for the continued support from our community, local councils, and partners.

"We are also incredibly grateful for our partnership with Bournemouth, Christchurch, and Poole Council, whose experience and expertise will greatly benefit this project."

In May, EDDC formed a new shared service with Bournemouth, Christchurch, and Poole Council, creating the South West Flood and Coastal team.

This brings additional specialist staff and experience from similar projects to help drive the scheme forward.

Contractors and suppliers have already visited the site and will be invited to tender for the work later this summer.

A contractor is expected to be appointed by the end of 2025.

Detailed design work will follow, including further engagement with residents and stakeholders.

Construction is now expected to begin in 2027, following delays linked to planning and resource challenges.

The scheme will be delivered in two stages.

The first stage covers design, evaluation, and securing the necessary consents.

The second stage will involve final construction preparation and building works.

The EDDC-led advisory group includes community representatives and stakeholders who help communicate local views and support the project.

A project board, including the Environment Agency and other partners, is overseeing delivery and funding.

The £21 million project is funded by the Environment Agency, local councils, and community groups.

The scheme is designed to save money in the long term by reducing flood risk and the impacts of climate change.